RAMPS OF THE BRIDGE OVER RIONI CHANEL
Zestafoni- Kutaisi-Samtredia Highway (E 60) Section: New Kutaisi Bypass KM 0+000 - KM 17+300 

    
Customer: 
Design was Developed by TRANSPROJECT Ltd: 
Design of the Retaining Walls:  

Geotechnical Survey was Carried out by: 
Contractor: J.V. Todini, Takenaka    
Subcontractor - AKKORD-GEORGIA: 
Engineer - J.V. PADECO:   

Project includes erection of 2 ramps (4 Reinforced Earth retaining walls).

Total area is about 600 sq. m.

Implementation of this project was finished in May, 2014